THE BRENNER PASS:

THE MOST IMPORTANT ALPINE CROSSING


In the early Bronze Age, around 1,700 CE, this mountain pass was an important commercial link between the North Sea and the Mediterranean countries.

 

In the 14th century, 3,000 tons of freight including spices, wine, sugar, oil and cotton were transported over the Brenner Pass every year. The flow of goods over the Brenner increased constantly, so that by the beginning of the 19th century the volume of goods being carried over the Brenner every year, using horse-drawn wagons, had risen to 15,000 tons and then to 60,000 tons only 50 years later. This soon led to capacity bottlenecks and the construction of the Brenner Railway.

The current route  was built between 1860 and 1867. A hundred years later, the motorway was built. Since 1974, the Brenner Pass can be crossed on the Austrian A13 and the Italian A22 motorways. After completion of the motorway, ten million tonnes of goods were transported across the Brenner Pass each year; today, around 40 million net tonnes are transported by road.

PROJECT MILESTONES

20.08.2007     

    

Baubeginn Zufahrtstunnel Mauls (Italien): 1,8 km, 9,3% Steigung, 92 m² Ausbruchsquerschnitt, Sprengvortrieb

 

28.04.2008

 

Start maschineller Vortrieb Erkundungsstollen Aicha (Italien): 10,5 km, Doppelschildmaschine (6,3 m Durchmesser)

 

23.10.2009

 

Fertigstellung des Zufahrtstunnels Mauls (Italien)

 

04.12.2009

 

Beginn der Bauarbeiten in Österreich: Erkundungsstollen Sillschlucht: 5,4 km, Querschnitt 26m², Sprengvortrieb

 

16.07.2010

 

Baubeginn Zufahrtstunnel Ahrental (Österreich): 2,4 km, 120 m² Ausbruchsquerschnitt, Sprengvortrieb

 

03.11.2010

 

Durchschlag Erkundungsstollen Aicha (Italien)

 

04.04.2011

 

Baubeginn Baulos Wolf I (Steinach am Brenner, Österreich): Logistiktunnel Saxener Tunnel und Padastertunnel

 

19.09.2011

 

Vortriebsbeginn Zufahrtstunnel Ampass (Österreich): 1.350 m, 35 m² Ausbruchsquerschnitt, 10% Steigung, Sprengvortrieb

 

07.10.2011

 

Beginn der Bauarbeiten am Baulos "Periadriatische Naht" (Italien): 3,7 km Haupttunnel, 1,5 km Erkundungsstollen, Auftragsvolumen 53,1 Mio. Euro

 

24.06.2011

 

Durchschlag Padastertunnel (Baulos WOLF I, Steinach a.Br./Österreich)

 

24.02.2012

 

Durchschlag Saxener Tunnel (Baulos WOLF I, Steinach a.Br./Österreich)

 

11.10.2012

 

Fertigstellung Zufahrtstunnel Ahrental = Durchschlag Zufahrtstunnel Ahrental zum Erkundungsstollen Sillschlucht (Österreich)

 

01.07.2013

 

Fertigstellung Zufahrtstunnel Ampass (Österreich)

 

04.12.2013

 

Beginn der Vortriebsarbeiten am Baulos Wolf II (Österreich): Zufahrtstunnel: 4 km Länge, 120 m² Ausbruchsquerschnitt, 10% Steigung Schutterstollen 950 m, Bauwerke Deponie Padastertal

 

11.12.2013

 

Fertigstellung Erkundungsstollen Sillschlucht (Österreich)

 

22.04.2014

 

Beginn Arbeiten am Schacht Patsch (Österreich) 180 m, Sprengvortrieb

 

04.09.2014

 

Fertigstellung Schacht Patsch (Österreich)

 

18.09.2014

 

Beginn der Bauarbeiten am Baulos Tulfes-Pfons (Österreich):380 Mio. Euro, 38 km, Bauzeit 55 Monate

 

31.10.2014

 

Beginn der Arbeiten am Baulos Eisackunterquerung (Italien): 301 Mio. Euro, 4,2 km Haupttunnelröhren, 1,8 km Verbindungstunnel

 

14.02.2015

    

Durchschlag Schutterstollen 950 m Länge (Baulos Wolf II, Österreich)

 

19.03.2015

 

Anschlag der beiden Haupttunnelröhren im Ahrental (Baulos Tulfes-Pfons, Österreich) im Beisein von EU-Kommissarin Violeta Bulc und der Verkehrsminister der 7 Alpenländer

 

25.03.2015

 

Fertigstellung Baulos "Periadriatische Naht" (Italien)

 

26.09.2015

 

Beginn maschineller Vortrieb Erkundungsstollen Ahrental-Pfons (Österreich):
17 km, 200 m lange offene Grippermaschine, 8 m Durchmesser

 

22.12.2015

 

Fertigstellung Zufahrtstunnel Wolf

 

05.01.2016

 

Beginn Vortriebsarbeiten Erkundungsstollen Wolf

 

06.12.2016

 

Beginn der Vortriebsarbeiten im Baulos Mauls 2-3: 993 Mio. Euro, 40 km Haupttunnelröhren, 15 km Erkundungsstollen, 10 km Logistik- und Verbindungstunnel, Bauzeit 7 Jahre

 

11.05.2017

 

Baulos Tulfes-Pfons: Durchschlag Verbindungstunnel Ost

 

04.07.2017

 

Baulos Tulfes-Pfons: Durchschlag Verbindungstunnel West

 

20.07.2017

 

Baulos Tulfes-Pfons: Durchschlag Rettungsstollen Eisenbahnumfahrung Innsbruck

 

04.12.2018

 

Durchschlag des Südportals in Franzensfeste

 

02.02.2019

 

Beginn der Vortriebsarbeiten des Bauloses Pfons-Brenner: 966 Mio. Euro, 37 km Haupttunnelröhren, 9 km Erkundungsstollen, 6 km Logistik- und Verbindungstunnel, Bauzeit 6 Jahre

 

12.02.2019

 

Baulos Tulfes-Pfons: Durchschlag Evakuierungsstollen Ahrental

 

29.03.2019

 

Tunnelanschlag "Erkundungsstollen Süd" von Wolf bis Brenner

 

30.04.2019

 

100 Tunnelkilometer sind ausgebrochen

 

22.05.2019

 

Baulos Mauls 2-3: Start der letzten der drei TBM, die den BBT in Richtung Süden ausbrechen: Nach Serena (5.5.2018) und Flavia (16.4.2019) macht sich Virgina auf ihren ca. 14,3 km langen Weg. Das Ziel aller drei TBM ist die Staatsgrenze am Brenner

 

01.07.2019

 

Tunnelanschlag Baulos Pfons-Brenner

 

29.11.2019

 

Der BBT ist zur Hälfte ausgebrochen

 

01.03.2020

 

Inbetriebnahme Unterwerk Ahrental durch Innsbrucker Kommunalbetriebe (IKB) und BBT SE

 

06.07.2020

 

Durchschlag des Erkundungsstollens im Bereich Steinach am Brenner

 

03.08.2020

 

Start Baulos Sillschlucht: Errichtung von Bauwerken hauptsächlich ober Tage

 

15.10.2020

 

Baustelle Eisackunterquerung: Vortriebsbeginn unter dem Fluss

 

10.11.2020

 

Baustelle Eisackunterquerung: Erster Durchschlag unter dem Fluss Eisack

 

08.02.2021

 

Baustelle Eisackunterquerung: Abschluss Verlegung der Eisenbahngleise der Bestandsstrecke

 

11.03.2021

 

Baustelle Eisackunterquerung: Beginn Vereisung der ersten Hauptröhre

 

28.10.2021

 

Tunnelanstich künftiges Nordportal: Innsbruck-Sillschlucht (westliche Haupttunnelröhre)

 

 

24.11.2021

 

Mit der Tunnelbohrmaschine "Serena" erreicht nach 3,5 Jahren und rund 14,2 km Vortrieb Richtung Norden erstmals eine Tunnelröhre des BBT die Staatsgrenze am Brenner - der Erkundungsstollen, 1.450 m unterhalb der Erdoberfläche

 

 

04.05.2022

 

Tunnelanschlag des Bauloses Hochstegen

 

 

19.05.2022

 

Mit dem Durchschlag zwischen den beiden Baulosen Mauls und Eisackunterquerung entsteht eine durchgängige Verbindung zwischen dem Südportal des BBT und der Staatsgrenze am Brenner

 

 

07.07.2022

 

Tunnelanschlag des Bauloses Sillschlucht-Pfons

 

 

30.03.2023

 

Baulos "H61 Mauls 2-3": Ankunft der Tunnelbohrmaschine "Virginia" an der Staatsgrenze am Brenner - nach 4 Jahren und rund 14,2 km Vortrieb des Haupttunnels Ost in Richtung Norden

 

 

02.05.2023

 

Baulos "H41 Sillschlucht-Pfons": Beginn des maschinellen Vortriebs der Tunnelbohrmaschine "Lilia" (Durchmesser 10,4 m) für 8,1 km Vortrieb im Haupttunnel Ost Richtung Süden

 

 

04.05.2023

 

Baulos "H53 Pfons-Brenner": Beginn der Vortriebsarbeiten 15,2 km Haupttunnel mit TBM, 10 km Haupttunnel Sprengvortrieb, 1,3 km Erkundungsstollen, 2,6 km Querschläge, Bauzeit ca. 6 Jahre, 959 Mio. Euro

 

 

27.06.2023

 

Baulos "H41 Sillschlucht-Pfons": Beginn des maschinellen Vortriebs der Tunnelbohrmaschine "Ida" (Durchmesser 10,4 m) für 8,4 km Vortrieb im Haupttunnel West Richtung Süden

 

 

04.12.2023

 

Baulos "H71 Eisackunterquerung": Abschluss der Bautätigkeiten

 

 

15.12.2023

 

Baulos "H52 Hochstegen": Abschluss der Bautätigkeiten

 

 

17.09.2024

 

Baulose „H41 Sillschlucht-Pfons" und „H21 Sillschlucht": Erster Durchschlag eines Haupttunnels in Österreich (Haupttunnel Ost)

 

 

18.09.2024

 

Baulos "H53 Pfons-Brenner": Beginn des maschinellen Vortriebs der Tunnelbohrmaschinen "Wilma" (Haupttunnel West) und "Olga" (Haupttunnel Ost) für ca. je 7,5 km Vortrieb Richtung Norden, Durchmesser je 10,4 m

 

 

05.12.2024

 

Baulos "H21 Sillschlucht": Abschluss der Bautätigkeiten

 

 

30.01.2025  

 

Baubeginn auf der Baustelle „Neue Zufahrtsstraße Riol“

 

 

02.05.2025

 

Baulos "H61 Mauls 2-3": Ankunft der Tunnelbohrmaschine "Flavia" an der Staatsgrenze am Brenner - nach rund 14,3 km Vortrieb des Haupttunnels West in Richtung Norden. Damit ist der maschinelle Vortrieb auf der italienischen Seite des BBT abgeschlossen.

 

 

20.05.2025

 

Baulose "H41 Sillschlucht-Pfons" und "H21 Sillschlucht": Durchschlag des Haupttunnels West

 

 

08.07.2025

 

200 Tunnelkilometer sind ausgebrochen

 

 

22.08.2025

 

Baulos "H41 Sillschlucht-Pfons": Ankunft der Tunnelbohrmaschine "Ida" nach rund 8,4 km Vortrieb des Haupttunnels West in Richtung Süden.

 

 

18.09.2025

 

Durchschlag des Erkundungsstollens zwischen den Baulosen „Mauls” und „Pfons-Brenner” an der Staatsgrenze am Brennerpass. Damit besteht erstmals eine durchgängige unterirdische Verbindung zwischen Österreich und Italien.

 

 

06.10.2025

 

Baulos "H41 Sillschlucht-Pfons": Ankunft der Tunnelbohrmaschine "Lilia" nach 8,1 km Vortrieb des Haupttunnels Ost in Richtung Süden.

 

 

OUR HISTORY IN PICTURES

Start of construction of the Mules access tunnel (Italy)
Start of mechanized excavation of the Aica exploratory tunnel (Italy)
Completion of the Mules access tunnel (Italy)
Start of construction in Austria
Start of construction on the Ahrental access tunnel (Austria)
Breakthrough on the exploratory tunnel in Aica (Italy)
Breakthrough on the Padaster tunnel (Wolf I construction lot, Steinach am Brenner /Austria)
Start of excavation on the Ampass access tunnel (Austria)
Breakthrough in the Saxen tunnel (Wolf I construction lot, Steinach am Brenner /Austria)
Completion of the Ahrental access tunnel = Breakthrough in the Ahrental access tunnel to the Sill Gorge exploratory tunnel
Start of excavation work on the Wolf II construction lot (Austria)
Completion of the Patsch shaft (Austria)
Start of works on the Isarco river underpass construction lot (Italy)
Start of excavation work on the Tulfes-Pfons construction lot (Austria)
Breakthrough in the 950 m spoil removal tunnel (Wolf II construction lot, Austria)
Start of TBM excavation of the Ahrental-Pfons stretch of the exploratory tunnel (Austria)
Start of excavation work on the Mules 2-3 construction lot
Tulfes- Pfons construction lot: Breakthrough east connecting tunnel
Breakthrough south portal in Fortezza
Start of excavation work on the Pfons-Brenner construction lot
Tulfes- Pfons construction lot: Breakthrough in the Ahrental evacuation tunnel
Start of excavations on the southern part of the exploratory tunnel from Wolf to Brenner
Mules 2-3 construction lot: Start-up of the last of the three TBMs excavating the Brenner Base Tunnel towards Brenner
Exploratory tunnel breakthrough in the Steinach am Brenner area
Isarco underpass construction site: Start of excavations below the river
Isarco underpass construction site: First breakthrough below the Isarco river
Isarco underpass construction site: Relocation of the existing rail line completed
Isarco underpass construction site: Start of ground freezing for the first main tube
Start of the excavation works at the future northern portal: Innsbruck - Sill Gorge (east main tunnel tube)
Start of excavations on the Sill Gorge-Pfons construction lot
Start of excavations on the Hochstegen construction lot
With the breakthrough between the Mules and the Isarco River Underpass construction lots, we now have a continuous connection between the southern portal of the BBT and the State border at Brenner Passr
Construction lot H61 Mules 2-3: Arrival of the TBM Virginia at the national border at Brenner Pass
Construction lot H41 Sill Gorge-Pfons Start of mechanised excavation with TBM Lilia
Construction lot H41 Sill Gorge-Pfons Start of mechanised excavation with TBM Ida
Construction lot H71 Isarco river underpass: Completion of the construction work
Construction lot H52 Hochstegen: Completion of the construction work