Currently, around 90% of the 225 kilometre long tunnel system has been excavated.
In order to construct the complex tunnel system efficiently, the BBT project has been divided into several construction sections, so-called construction lots. This makes it possible to proceed with multiple excavation methods simultaneously in different locations along the new line.
Of the total of approximately 225 kilometres of tunnel to be built, 207 kilometres have been excavated for the BBT tunnel system to date.
OF RAILWAY TUNNEL
OF SERVICE TUNNEL
ACCESS TUNNEL, RESCUE TUNNEL AND LOGISTICS TUNNEL
OF WHICH HAVE BEEN EXCAVATED TO DATE
There are currently three active construction lots, one of which is located in Italy and two in Austria.